Fact Checker Vera Files should be Fact Checked

Fact Checker Vera Files should be Fact Checked

0
254
Fact Checker Vera Files should be Fact Checked

Vera Files even failed to distinguish the difference between “began” and “completion”… lol their factual findings seems to contradicts theirs.

Vera is holding false information then! Misinformed? Or just wanted to misinform?

COMPLETE AND VERIFIABLE FACTS

*The LRT-2 East Extension Project was originally conceptualized in 1999, under the Metro Manila Urban Transportation Integration Study (MMUTIS);
*The project was two decades in the making, encompassing four (4) administrations;
*It was during the time of former Presidents FVR and Erap when the Master Plan that identified the need for the LRT-2 East Extension Project, the Metro Manila Urban Transport Integration Study (1996-1999) was developed;

*It was during the time of former President GMA when the LRT-2 East Extension Project was included in the investment program of the National Government, both in the 2005 Medium Term Philippine Development Plan (MTPDP) and 2009 Comprehensive Integrated Infrastructure Program (CIIP);

*It was (again) during the time of former President GMA when the series of feasibility studies that eventually led to the investment approval for the LRT-2 East Extension Project started (March 2010 Japan Study on Economic Partnership Projects in Developing Countries in FY 2009; October 2011 JICA Pre-Feasibility Study; July 2013 JICA Detailed Feasibility Study);

*It was during the time of former President PNoy when the NEDA Board Approval (04 September 2012), and the JICA Loan (27 March 2013) were secured, as well as the awarding of the 1st out of 3 construction contracts (viaducts; 23 December 2014); and,

*It was during the time of PRRD when the right-of-way acquisition (especially for the stations) was completed, the 2nd out of 3 constructions contracts (stations; 9 December 2016) was awarded, the 3rd out of 3 constructions contracts (electromechanical systems; 14 December 2018) was awarded, and the LRT-2 East Extension Project was completed for the benefit of the riding public.

So, again, as far as the LRT-2 East Extension Project is concerned, let me end by saying.

Thank you, Pres. FVR.
Thank you, Pres. Erap.
Thank you, Pres. GMA.
Thank you, PNoy.
Thank you, PRRD.
and Thank you, Filipino people! 🇵🇭

Please note, Vera Files, that even if the LRT-2 East Extension Project was approved by the NEDA Board on 04 September 2012, only 1 of the 3 construction contracts was awarded before the current Administration — i.e., the Viaducts Contract was awarded on 23 December 2014.

As of June 2016, 2 of the 3 construction contracts have not yet been awarded, and have not yet started any construction, manufacturing, and installation.

The contracts for the following were non-existent as of June 2016, and it was the current Administration that had to catch-up to award these:

The contracts for the following were non-existent as of June 2016, and it was the current Administration that had to catch-up to award these:

  • 2 Stations
  • Electromechanical Systems, which covers the following:
  • Trackworks
  • Power Supply System
  • Overhead Catenary System
  • Signaling System
  • Telecommunications System
  • Supervisory Control and Data Acquisition (SCADA) System
  • Automated Fare Collection System (AFCS)

In other words, ang nadatnan ng current Administration sa LRT-2 East Extension is the viaducts construction, na ongoing at hindi pa tapos. As of July 2016, ni kontrata wala pa para sa 2 stations, trackworks or riles, kuryente para sa mga tren, signaling and telecoms system, control system, at fare collection system.

from: Asec. Goddes Hope Libiran

🇵🇭